Case Studies

Resource Solutions Office Fit Out

12000 SQ FT | Salford

Office Fit Out For 200 Staff

A two-stage office fit out for Resource Solutions. This office set over two floors in Riverside, Salford, is home to the UK operations hub known as a Global Service Centre for the recruitment outsourcing firm. The UK GSC is home to almost 200 staff in a secure office.

Office Fit out For Resource Solutions

The office fit-out was phased by floor, as the business ramped up its own staff recruitment. In total RS occupy over 12000 sq ft in this newly fitted-out office close to the Manchester Media City development.

As a back office hub the Riverside office has a clean and timeless fit-out scheme. All finishes are chosen for high traffic, constant use. Although budget constraints meant some compromise the office interior has good quality FF&E that will withstand the usage.

Working in the Riverside development involved careful coordination with landlord ops staff to ensure minimal disruption to other occupiers. Having a good site manager makes a difference to working with our neighbours.

Internal chinese walls meant the office floors are divided physically to create sub-groups within the back office space. Secure access has been incorporated to the sub-offices, and the spaceplan has shared communal spaces on both floors.

The phased fit-out scheme had an overall 12 week duration made up of two 6-week phases.

To see more information about the fit-out services of fusion Office design click here

robert-walters-logo
three-logo
baseware-logo
collinson-group-logo
g4s-logo
allianz-logo
Book a consultation to get started with your project